Marc Sanford’s Eagle Project
Refurbish the basketball court at the Middletown Village School
Phase One
When: 29 Sep 2012, 11AM - 3PM
Where: Middletown Village Elementary School (see below)
What:
- Clean the court
- Fill in the cracks in the asphalt
- Repaint the backboards and supports
Phase Two
When: October 14, 2012 at 10:00AM
Where: Middletown Village Elementary School (see below)
What:
- Completely reseal the basketball court at village school.
- Lunch included
- We will be working with sealant, so please wear old clothing and shoes
Phase III When: October 14, 2012 at 10:00AM
Where: Middletown Village Elementary School (see below)
What:
- Finish paint on backboards
- Stenciling hopscotch
- Stenciling 4 courners
Phase IV
When:
Where:Middletown Village Elementary School
What:
- Stenciling basketball lines